South Main Street Reconstruction
In January 2015, the City engaged HMH to prepare PS&E for pavement reconstruction, sidewalk repairs, accessibility upgrades and traffic signal improvements on a very accelerated schedule. To meet funding deadlines, HMH prepared plans, specifications and estimates for the 1.2 mile long project in approximately six weeks, using expedited submittals and “over-the-shoulder” reviews to accomplish City approval for advertising.
An important design challenge was lowering the crown of the street to reduce excessive cross-slope. The center of South Main Street includes old concrete pavement overlaid with layers of asphalt concrete over many years, such that shoulder grades were up to 10% at certain locations. HMH developed a solution to grind off all the old asphalt concrete, and replace it with a much thinner “sandwich” section of pavement mat between two asphalt concrete lifts, which substantially reduced the height of the crown and the cross-slope.
Services
- Public Works
- Stormwater Compliance
Location
Milpitas, CA
Completion
2015
Key Facts
- Client: City of Milpitas
- Fast-track PS&E preparation in approximately six weeks.
- Innovative pavement reconstruction with paving mat to limit thickness over buried concrete slab pavement.
- Accessibility upgrades to current ADA requirements.
- Partial “table-top” intersection to improve pedestrian accommodation at intersection of South Main Street and Serra Way.